Vår Energi aims to boost production through infill drilling, exploration and tie-backs by deploying the Jotun FPSO.
Production is expected to begin by the end of second-quarter 2025, with an expected 3-4 months ramp up period to peak ...
Couldn't resolve component "default" at "/:pathMatch (.*)?/:lcsId ( [0-9]\- [0-9]\- [0-9]+| [0-9]- [0-9]- [0-9]+PT [0-9]+)" ...
Vår Energi has started the tow out of the Jotun floating production, storage and offloading vessel (FPSO) from the Worley ...
The Balder X project is on track for the start of production by the end of the second quarter, the company said. Vår Energi’s Jotun floating production, storage and offloading vessel (FPSO ...
The FPSO will be installed at the Balder field in the Norwegian North Sea, and once online by the second quarter of this year, it will push production up almost four times current output to 80,000 ...
In reaching the decision to delay Balder X, a key consideration was to limit as much as possible the carryover of work on the Jotun FPSO into the offshore installation and start-up phase.